Updates:
7/23/2024 site work and security update
Direct email contact for site-related matters: [email protected]
Press Releases:
8/15/2023- Rivian Project Chargers Ahead, Court Agrees
5/2/2022- Economic Development Agreement signed
4/29/2022- State and JDA file environmental permit application and plan for construction
4/26/2022 JDA approves Economic Development Agreement
3/14/2022 Georgia Department of Economic Development Announces Committees
2/28/2022 Georgia Chamber press release regarding polling results- Rivian project supported by a 2-1 margin
2/21/2022- Georgia Department of Economic Development Responds to Local Leadership Regarding Rivian Project- State and JDA letters included
2/18/2022 Public Statement regarding Morgan County and Social Circle Zoning Hearings
2/10/2022- Supplemental Zoning Package with key studies
1/31/2022- Public Statement regarding Walton County zoning
Articles
7/29/2022- Georgia Trend Article- interview with JDA Chairman
Economic Development Agreement
9/26/2023 First Amendment to Economic Development Agreement
9/26/2023 - Updated Summary of Incentives
5/2/2022- Economic Development Agreement
Project information:
**Updated 2/28/2023**: Answers to frequently asked questions
Rivian Announcement Information
Site Studies and Reports
Programmatic Agreement-SHPO
Environmental Assessment - USACE
Tree Survey
U.S. Fish and Wildlife IPaC Resource List
Traffic Study
Georgia EPD Air Permit Application
Tribal Notification Letters
Hydrology Study/Stormwater Masterplan
Response to Comments to Section 404 Permit
Preliminary Geotechnical Report
Geotechnical Site Investigation
Threatened and Endangered Species Report
Community Letters of Support
Ground Water Recharge Plan
Technical assessment of potential impacts to groundwater availability by Nutter & Associates
Development of Regional Impact Application
Development of Regional Impact Report
Grading Plans
Grading Plan Set- last updated June 2023
Site maintenance, security and environmental compliance
Following Rivian's announced pause in construction in early 2024, the below documents detail actions planned to maintain, secure, and ensure environmental compliance in agreement with the JDA and State. Leading up to the start of vertical construction, activity at the site will continue with the contracted construction company, which will maintain a constant presence there.
March 22, 2024 Letter from State and JDA to Rivian
April 19, 2024 Summary of Rivian Response
April 18, 2024 Letter response from Rivian to State and JDA
7/29/2022- Georgia Trend Article- interview with JDA Chairman
Economic Development Agreement
9/26/2023 First Amendment to Economic Development Agreement
9/26/2023 - Updated Summary of Incentives
5/2/2022- Economic Development Agreement
Project information:
**Updated 2/28/2023**: Answers to frequently asked questions
Rivian Announcement Information
Site Studies and Reports
Programmatic Agreement-SHPO
Environmental Assessment - USACE
Tree Survey
U.S. Fish and Wildlife IPaC Resource List
Traffic Study
Georgia EPD Air Permit Application
Tribal Notification Letters
Hydrology Study/Stormwater Masterplan
Response to Comments to Section 404 Permit
Preliminary Geotechnical Report
Geotechnical Site Investigation
Threatened and Endangered Species Report
Community Letters of Support
Ground Water Recharge Plan
Technical assessment of potential impacts to groundwater availability by Nutter & Associates
Development of Regional Impact Application
Development of Regional Impact Report
Grading Plans
Grading Plan Set- last updated June 2023
Site maintenance, security and environmental compliance
Following Rivian's announced pause in construction in early 2024, the below documents detail actions planned to maintain, secure, and ensure environmental compliance in agreement with the JDA and State. Leading up to the start of vertical construction, activity at the site will continue with the contracted construction company, which will maintain a constant presence there.
March 22, 2024 Letter from State and JDA to Rivian
April 19, 2024 Summary of Rivian Response
April 18, 2024 Letter response from Rivian to State and JDA